H/Benning Construction

Phase 2 of DC Streetcar construction along H Street/Benning Road started in December 2012 and is now complete!

About 80 percent of the work to make H/Benning streetcar-ready was completed during Phase 1 in 2011, during the Great Streets roadway reconstruction project. Testing of the DC Streetcar system began in December 2013 and continued throughout construction in 2014. DC Streetcar is now in the final phase of testing before passenger service can begin.

Residents with construction or testing questions can still call our 24/7 construction hotline  at (202) 210-3700. Archived construction notices will remain here.

 

Construction Highlights

 

H/Benning Construction Impact Areas

 

Hopscotch Bridge – 3rd/H Streets NE

2014-03-19 OIW and Inekon cars at WT

DC Streetcar’s Western Turnaround is atop the Hopscotch Bridge. Major construction at 3rd Street NE and H Street NE closed the intersection for several months, but was reopened for pedestrians and vehicular traffic in February 2014. The construction of pedestrian ramps and other work around the Union Station garage entrance occurred in the fall of 2014. DDOT’s Ralph Burns talks about pedestrian safety at this completed intersection here:

 

Midline Substation – 12th/H Streets NE

Midline Substation

 

In May 2013, the Commission of Fine Arts (CFA) approved the design (as seen above) for the Midline Station at the southwest corner of 12th and H Streets NE. The substation is adjacent to Khan’s Bar & Grill. The substation was installed in mid-October. Construction on the brick enclosure and façade treatments was completed in summer 2014. DDOT’s Thomas Perry shows off the completed midline substation:

 

Pocket Tracks – 21st-24th Streets/Benning Road NE

2014-02-20 concrete curbs at PT 3

The pocket tracks will allow streetcars to enter and exit the Car Barn Training Center once the streetcar is up and running. Train control testing, storm filters, track tie-ins and utility work were completed in summer 2014.

 

Track Switches – 26th Street/Benning Road NE

Rail Switches

Streetcar track switches were installed on westbound Benning Road for the Eastern Turnaround. To facilitate this work, 26th Street was closed in August 2013 and reopened in January 2014.

 

Overhead Catenary System (OCS)

2014-02-20 NRSC-3 CBTC section insulator 3

Erection of the OCS poles, which hold wires that power the streetcars, was completed in late 2013. Stringing of contact wire from the OCS poles began in November 2013 and wrapped up in early 2014.

H/Benning Construction Photos

Facebook Twitter Plusone Email